Item Coversheet

  Town of Huntersville
REQUEST FOR BOARD ACTION
12/19/2016

REVIEWED:

To:                  The Honorable Mayor and Board of Commissioners

From:              Michael Jaycocks

Subject:          Recreation Center Guaranteed Maximum Price


The Recreation Center Project will include 23,577 sq. ft. of indoor recreation space.  The center will house two full-sized basketball courts, four volleyball courts, bleacher areas, civic room, lounge/café, restroom facilities and storage areas.   The project also includes rerouting the current walking trail and building the new driveway off of Verhoff Drive that will serve the center and connect to the new parking lot on CPCC property.

 

The Town Board approved Rodgers Builders as the Construction Manager at Risk for this project on June 15, 2015.  Below is a time table on the revised cost throughout the design process.

 

August 25, 2015- 30,557 sq ft-  Cost: $7,929,919

September 19, 2015- 30,557 sq ft.- Cost $6,494,595-  This cost reduction was due to changing the location of the center from the property along Hwy 21 to the currently location on Verhoeff Drive.

October 13, 2016- 23,577 sq ft. - Cost $6,119,992

December 6, 2016- 23,577 sq ft. - Cost:  $5,704,845- Final GMP


ACTION RECOMMENDED: 

Approve the Guaranteed Maximum Price from Rodgers Builders, Inc. 

 
 
FINANCIAL IMPLICATIONS:

$5,704,845

 



ATTACHMENTS:
DescriptionType
Guaranteed Maximum PriceBackup Material